Hello,
I need to organize all the issues of my project. I have use Epics that represents my main features. But, beyond the epics I need to organize the issues in a more granular way that represents the functionalities of the system.
How can I do this? (I already used components and labels to other things)
Another question, how can I change a Epic link from a closed issue from a closed sprint? I need to Re-open the issue? Does this have impacts on the jira reports?
Many Thanks,
Best Regards,
Nuno Gomes
Hello @Nuno Gomes - I can give you insight into how my team operates Jira but in the end, configuration is changed per company to best fit the teams needs. I think you may need to better identify your project and epics based on your current organization. Here is some insight into how we operate:
Organization
Question
To answer your question regarding "Another question, how can I change a Epic link from a closed issue from a closed sprint? I need to Re-open the issue? Does this have impacts on the jira reports?"
Depending on which reports you are running, the change may show up. If you are running a report by LastUpdated or EpicLink, that yes these changes would be reflected.
Thanks
~Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.