Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Time Tracking report accuracy incorrect

Harriet Hirst
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 4, 2018

I use the Jira Time Tracking feature against each ticket in a project. 

I produce the Time Tracking report each week to assess how on track we are. 

Currently, Jira tells me the DEV team are over by 2d 7h 4m in the web interface. When I export this to excel and do a sum on the Accuracy column (which is in minutes) I get a different value, the total being -1564, which is actually just over 26 hours, so in pretty time, 3d 2h...

I've double checked that the Accuracy column is correct by doing the following calc:

original time estimated - total time spent

This leaves me with the same value.

All the other columns sum to the same value (in minutes) as the web interface shows in pretty time. 

I need to understand why there is a difference here as I have to report to our board whether the team are over budget and by how much. 

1 answer

0 votes
Marcel Lange
Contributor
September 23, 2021

Hello,

did you ever find out, what the Problem was? 

Suggest an answer

Log in or Sign up to answer