Jira agile sprint finalization

Ron Grinfeld January 8, 2017

This question is in reference to Atlassian Documentation: Configuring sub-tasks

I'm using a another status for subtasks named 'Failed'.

I mapped the status on the workflow to the 'Done' category.

Now, when I try to complete a sprint and there is a story (in Done status) that has a subtask in 'Failed', Jira will not let me complete the sprint claiming that there are incomplete subtasks in it.

Am i missing something or is Jira Agile looking for the explicit 'Done' status of subtasks ?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 8, 2017

The exact status isn't too important, and nor is the status category.

Try reconfiguring the board, putting the "failed" status into the far-right hand column on the board.

Ron Grinfeld January 8, 2017

Thanks !!!, works.