Jira jql query find added, deleted, carried over stories in 5 sprints?
Please mail suggestions to my email
Hi @Saaketh kk - Unfortunately, this is not possible with simple JQL. There are several long-standing suggestions around extending JQL to better support sprint-based queries.
Your best bet is to simply look back at the sprint reports for the last 5 sprints. This will give you the detail of what was added/removed after the sprint began. You could also copy/paste the table portion of the reports into Excel and manipulate as needed from there.
Yes. JQL doesn't really support this because it's not something people doing Scrum would usually need. It asks a question about the question - of what use is this search to your Scrum teams?