I have 2 Jira boards, let's call them Team A and Team B.
The Velocity Chart for Team A includes a sprint for Team B, for no apparent reason.
The incorrect sprint shows zero committed and zero completed on the Team A Velocity Chart, however it shows correctly on the Team B board's Velocity Chart.
When I click on the incorrect (Team B) sprint on the Team A Velocity Chart, it shows details for one of the Team A sprints.
I have re-indexed both projects but that did not make a difference.
How can I remove the incorrect sprint from Team A's Velocity Chart?
Hi,
I had the same issue while configuring a new board for a new team. This means that you have issues from the other board in your backlog.
What I did was just filter the issues by component :
And voilà ! (if I dare say)
Just note that this works only if no issue is in both boards (ex: issue n°14 is in board A and Board B)
I hope this helped you !
Regards,
Vincent
Thanks very much Vincent! Will give this a try.
Regards,
Elmarie
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Filter by the sprint of Team B and check if it have any issue that belongs to Team A
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.