Kanban board adding columns up by Story Points

David Barr
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 25, 2022

Is there a way to get a Kanban board adding columns up by Story Points & setting a limit?

3 answers

2 votes
Laura Holton _ACE Manchester_
Community Champion
January 25, 2022

Hi @David Barr 👋

Welcome to the Community! It appears this feature or something very similar has been raised as a suggestion, you can view, vote and monitor the ticket here: https://jira.atlassian.com/browse/JSWSERVER-12495

I hope this helps but if you have any other questions just ask away 😃

All the best,

Laura

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 25, 2022

Don't hold your breath.  Kanban does not use Story Points or most other numbers as estimates, doing this would mean you're not doing Kanban any more.  Atlassian don't tend to build stuff that supports doing not-Kanban with a Kanban board (or not-Scrum with a Scrum board)

0 votes
Marion Hederer April 8, 2022

And what about using Scrum Boards? I'm not able to set WIP limits based on story points. Any suggestions? 

 

Kind regards,

Marion 

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 9, 2022

Scrum doesn't have work in progress limits, because the sprint does it for you, by definition.

When you plan a sprint, you are committing to completing the stories you have put into a sprint.   You would have put in only stories you believe you can complete in the timeframe, based on their estimates. 

So you don't need to control the amount of issues in the columns - by definition anything on the active board is within the limits you set.

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 25, 2022

Hi @David Barr -- Welcome to the Atlassian Community!

Short answer: that is not possible with Jira Cloud, out-of-the-box.

Follow-up: 

  • What problem are you trying to solve by doing that? 
  • What would that limit you note represent?  Teams using Kanban practices typically manage work in progress (WIP) limits by item count...although they may use additional indicators for queue replenishment.

Kind regards,
Bill

Parcandi Administrator April 7, 2022

Hi @Bill Sheboy ,

we're wishing to see the same functionality. 

What we're trying to solve is: We want to limit the amount of complexity in a column. We use story points to estimate the complexity.

What are your thoughts about that?

Kind regards

Ralf

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 7, 2022

To limit the complexity, limit the number of cards in a column.

Like Bill Sheboy likes this