Hello,
we have Jira Project Management Sofwtare V: 9.12.4 (Data center )
Since several weeks, users experience slowdowns, from a few seconds to a few minutes.
This is our configuration:
28 gigas of total memory (RAM)
10 gigas allowed for Jira
Java: 11
Is our configuration sufficient to ensure the proper functioning of Jira?
Sincerely
You should check with the recommended hardware as it depends on different things :
https://confluence.atlassian.com/jirakb/jira-server-sizing-guide-975033809.html
In an other hand do you have some error or time out visible from the application log ?
Which database type are you using ?
regards
I don't have details but one possible solution is compress the packet before transmitting it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.