Move complete epic to sprint

Peter Moser
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 12, 2017

Hello, 

is it possible to move all tasks and stories from an epic to a sprint? We often have the requirement to develop a whole epic in a sprint, so this would be a nice feature. 

 

Best regards,

Peter

1 answer

1 accepted

5 votes
Answer accepted
Jakub Lazinski
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 13, 2017

Hey Peter, how about:
* filtering issues in your backlog by the Epic you're interested in moving to a Sprint; you can do it by using the Epics tab on the left hand side
* once filtered out, select all issues in Backlog
* right click on any of them and select Move to Sprint