One of the team members accidently changed the epic into a bug - this had the effect of removing all child stories (is this a defect?)
So I'm trying to restore it, however I cannot find a way of putting the closed stories into the epic, as they do not appear on the plan view.
This extremely frustrating.
How can I move closed issues into an epic?
Hi Colin,
I wouldn't say that's a BUG, but there's certainly room for improvement. That's why I filed an improvement request at https://jira.atlassian.com/browse/JRA-32134
As for now, you can use the workaround below:
1. Open the Epic issue, and in the activity tab click on "All" or "History". With that you'll be able to see all children issues that were associated with it at some point.
2. Open all children issues that do not appear on the board (already closed), and re-open them.
3. Go to the board and associate them again with the Epic parent.
4. Close again those issues that should be closed.
I know that this can be quite frustrating, but I hope it helps for now.
This is really not a solution (using no less than 3 different screens) - we have over 100 closed issues and this is likely to make my day a lot less productive. I was hoping that the tool would put me in charge and not the other way around.
If the tool allowed me to assign the epic from inside of the view/edit issues screen this might not be a problem (GHS-6854, GHS-6539).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.