My time JIRA Time-Tracking Report is not picking up logged time on issues and sub tasks! HELP!

Shaun Loh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 29, 2018

Hi all,

I've set up a project in JIRA. I want to see on all the time spent on each item and also a rolled up total time per epic.

Things I have tried:

  • Configuration
    • Have added users with permission to "work on issues" to enable time logging
    • Have enabled the time-tracking feature in settings
  • Ran Basic Time Tracking Report
    • Logging time to issue types Story / Subtask / Task
    • Running Time Tracker Report with no results
  • Adding a Version
    • Added an Issue & Subtask to a new version I created
    • Selected that version in the TIme Tracker Report
    • Still no results

Seems like a pretty basic function of reporting on logged time. I am a little stumped as to why this isn't working. Have I configured something incorrectly?

All feedback appreciated.

Thanks in advance, Shaun.

1 answer

1 vote
Fazila Ashraf
Community Champion
February 25, 2018

@Shaun Loh , To roll up the effort spent on the hierarchial tree up the related epic , in my organization, we use the Structure plugin's view => https://wiki.almworks.com/display/structure/Progress+Based+on+Time+Tracking 

Shaun Loh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 26, 2018

Thanks Fazila, i'm looking to use the  normal Time Tracker Report in JIRA, i'll look into the structure plug-in. Cheers