Need Solution to Prevent devs change original estimates of tasks

Zainab Hassan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 18, 2023

As the project manager, I'm exploring ways to prevent others from changing the initial task estimates while still allowing the logging of hours. Any suggestions or solutions would be appreciated.

1 answer

0 votes
Miklos Tix
Contributor
October 27, 2023

Hi @Zainab Hassan

I think you can remove the time tracking field from the Edit screen and just leave it on the View screen and then you can add a transition screen with the Time Tracking field and set  a condition for the transition and allow only users that you want to edit the original estimation.

The transition can point to the same status so it won't change.