I would be needing help in creating a dashboard which will help me in showing Committed vs Actual vs "Scope Change During Sprint" story points.
I know that in JIRA Committed vs Actual is available but how can I show this third value also along with the existing one.
I am attaching a picture also which I have created in excel, but I want the same to be created in JIRA automatically
Hi @Ankush Goel
Try our Great Gadgets app. It includes a Team Velocity gadget that display also the Scope Change along with Initially and Finally Committed story points. It also includes a data table for every sprint.
Danut.
Hi,
I can suggest an app for that, however it does not have the scope change display functionality - https://marketplace.atlassian.com/apps/1219761/individual-velocity-report-chart-gadget
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thats really helpful but for the individual one and for committed vs actual.
My question is still there on how to calculate for after scope change points.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.