I have a Greenhopper rapid board for my project and am using the GreenHopper simplified workflow.
When I drag a Techical Task (with a few hours estimated work remaining) to the Done column, the remaining time is not set to 0h.
Naturally, I understand with the JIRA default workflow, one can add a post-function to the Closed status to automatically set this value to 0h, but in my case the workflow is not manually editable AFAICT.
Can someone help or advise on a work-around for this?
Many thanks in advance.
I had to do the following to get to where I wanted to be:
1. Create a copy of the default workflow for my organisation
2. Add a post-function to the resolve transition which clears the "Remaining estimate" field -- don't forget to publish it! ;-)
3. Create a new workflow scheme and apply it to my project
Happy now.
Log Work Utilities add-on allows to clear remaining estimate on issue close/resolve without a need to modify workflow: https://marketplace.atlassian.com/plugins/com.gebsun.plugins.jira.log-work-utilities/server/overview
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.