I am not able to log work,
I have set Estimation -> Timetracking to "Remaining Estimate and Time Spent"
Check following:
- Ensure time tracking is enabled globally
- You have permission to log work. You may not have permission to log work even if you are an administrator.
Thank you solved it :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Could you mark the answer as accepted?