Not able to see the option to complete the sprint

Gowrisankar Y
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 21, 2021

When I am trying to end the sprint, not able to see the option to complete sprint as it is greyed out, though I am an admin to project and the board

2 answers

0 votes
Mayur Jadhav
Community Champion
October 21, 2021

Hi @Gowrisankar Y 

Welcome to the Atlassian Community!!!

Even if you are admin of Project or Board but if you don't have Manage Sprint Permission you will not allowed to Start/ Stop Sprints.

 

Here is the link for Atlassian Documents for Jira Project permissions : https://confluence.atlassian.com/adminjiraserver/managing-project-permissions-938847145.html

 

 

Regards,

Mayur

0 votes
Robert Wen_Cprime_
Community Champion
October 21, 2021

Hello, @Gowrisankar Y ! Welcome to the Atlassian Community!

 

On a company-managed project, you should check and see if you have the Manage Sprints permission.

Suggest an answer