is it possible that i have About 5 Kanban Board. I have a Tasks that must be in Two Boards at the same time. If the Task went to an other Status it must be changed the Status in every board. It would be great when a Task is linked to a Story that the Story will be showed in every Board ?
Maybe one of you can help me.
thanks and Regards
Patrick
A board is just a view into the data, driven by the boards filter.
So ... if you have 5 boards and the filter for each board includes a specific task, then you will see it on each board. Also, if the status of that task is changed on one board, it will update correctly on all the other boards. The only time that it wouldn't show correctly is if the status isn't mapped to a column of the board.
I'm not totally sure about your comment with the story, but again, if the board filters include that story, it will show.