Really big issue here. I am on the latest release of JIRA and Greenhopper.
I have a whole bunch of Epics. We went through the process of doing Epic / Story breakdown, so I have a whole set of Stories related to Epics. I created the Stories using the "Create Issue In Epic" from the Plan mode of a Rapid Board.
Now, I have an enormous issue. I cannot re-order stories independent of Epics.
For example, imagine that I have two epics:
The huge problem is that I cannot order the stories in the backlog in the Rapid Board Plan mode independent of the Epic!
In other words, I cannot have the following in my backlog:
I can re-order by drag-and-drop, but it is not saved in JIRA. If I click out of the board, then click back in, the "re-order" that I attempted is not saved.
Worse, I cannot even add a single story to a Sprint from further down in the backlog.
I do not see this for stories that are outside of an Epic.
Help!
(Copying the comment in HJ-1225)
Paul, apparently, you have a structure with GreenHopper synchronizer installed, and that synchronizer is configured to sync both Rank and Epics.
This means that there's a structure that contains a hierarchy similar to what you gave in your example. With that configuration, it's impossible to mix stories from different epics in a single sprint - because their "backlog/sprint" order (Ranking) is synchronized with their position in the structure - which is below their respective epic.
In more detail, here's what happens:
As a workaround, you generally have 3 options:
If you need to both manage epic hierarchy AND backlog in Structure, and need epics span multiple sprints, the only option is to have 2 structures: one for epic hierarchy management, the other one, flat, for stories backlog management.
Hope this helps!
Igor
Hi Paul,
You definitely should be able to reorder stories independently of Epics.
It could be a couple of things:
* It's not possible to drag stories OUT of an active sprint - are the stories you are trying to re-order all in the backlog?
* You need Schedule permission to re-rank stories, can you check that you definitely have this? (although you do say you can rank other stories, so unlikely this is the cause but worth checking)
* Your board filter could be set to order by something other than Rank (again, unlikely as you said it works for other stories) - if this is the case, you would see a message on your configuration > Filter tab saying Ranking is disabled, as the Filter Query is not ordered by Rank.
If none of these are the problem, I suggest contacting Atlassian Support at https://support.atlassian.com, and they can help you figure out what's going wrong.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your info. I found out the problem. For some reason, the ALM Works Structure Plugin was causing this behavior. I created a separate JIRA project and I was unable to reproduce the same, so I knew it was something in my environment.
On a whim, I disabled the Structure Plugin in my JIRA installation and all of a sudden everything worked.
I created a support issue with ALM to see if they can help me further. For now, I will do without Structure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Glad you sorted it out! Thanks for the info - useful to know.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.