Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Products
  • Jira
  • Questions
  • Our program has a requirement to estimate Tasks and Sub-Tasks using Story Points. How do I enable the Story Points field for Tasks and Sub-Tasks?

Our program has a requirement to estimate Tasks and Sub-Tasks using Story Points. How do I enable the Story Points field for Tasks and Sub-Tasks?

Christie Dziubek
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 18, 2015
 

1 answer

0 votes
Damian Skrodzki
Contributor
June 18, 2015

Here is the instruction how to enable Story Points for chosen issue type:

  1. Navigate to the Custom Fields page, locate Story Points custom field and choose cog icon > Configure.
  2. Locate the context named Default Configuration Scheme for Story Points and click the Edit Configuration link.
  3. Under Choose applicable issue types, select the issue type(s) which you want to estimate.

Source: https://confluence.spartez.com/display/AEFJD/Enabling+Story+Point+field+for+%27Bug%27+issues