Overdue tasks - new deadline

Nichol Pope
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 12, 2024

In Jira Business Project is it possible to:

 

a) show on 'timeline' a initial due date vs a extended due date

 

b) the end date in 'list' as red if passed

1 answer

0 votes
Christopher Maxwell
Community Champion
March 13, 2024

Hi @Nichol Pope , and welcome to the Atlassian Community Forums!

I believe your question relates to Jira Work Management, and, unfortunately, there is not any default capability for this.

Two thoughts here. One would be to add a few custom fields (one for original due date, and one for the modified due date). You could then create alerts/notifications based on those fields. However, this doesn't, by default, do anything with the timeline so doesn't really help you with what you need.

The second is to look into some of the marketplace options that relate to the "timelime" for Jira Work Management. Many of the apps have free trials, or you can contact the vendor to ask whether their app provides the functionality you are needing.