It's frustrating that the target start/end dates of my epics don't automatically change based on what I set the stories inside to be. Is there any way to make this happen? Additionally, you can't see a consolidated rollup of story points based on the total of the stories/tasks inside the epic, making it harder to plan.
Am I doing something wrong or is this a possibility?
If you go to 'View setting' over on the right of your 'plans' screen you can tick the box for 'Roll-up'. There's one for 'dates' and one for 'others'. then depending on the fields you bring in you'll see the relevant rollups.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.