I just stared using Portfolio 2.0, I used the wizard to connect it to our Board. We have Sprints on the Board that are serving to group Stories for purposes other than scheduling into a release. They're used as holding buckets to easily remember which Stories were deferred from a Release. The Stories in each of these "non Sprint" Sprints may be in many Epics. Is there any way to suppress these non-Sprint Sprints from coming into Portfolio? I tried emptying one and then deleting it from the Board, but it is still showing in Portfolio.
Hi Ericka,
Thanks for your question. Currently there is no way to suppress sprints from your connected boards. All sprints on your board will show in your plan.
When you delete a sprint it will be reflected in the schedule upon (re)calculation. However, due to technical limitations you will need to refresh your browser tab for the plan to fully reflect the deletion in all the drop-downs of the scope view.
I hope that answers your question.
Best,
Allard
thank you very much for taking the time to help me! much appreciated!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.