Hello
Whenever I create a dependency between Item the plan auto-adjust to it and signal the dependency on the report section.
However, after committing the changes such dependency is no longer visible on the live plan (even if it is on the issue details).
Any idea why, anyone?
Thanks,
Alex
Are you saying you don't see the visual indicator of the dependency on the timeline in Portfolio, or if you click an issue from your scope, you don't see the dependency listed in its detail view there?
I mean't the visual indicator of the dependency, e.g. in the plan the item are displayed in parallel instead of sequentially.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.