ABC-1(Story)
ABC-2(Epic)
ABC-1 is included into two versions
1. CPR 1.0 (Cross project release)
2. PSR 1.0 (Project specific release)
ABC-2 is part of only one version
1. CPR 1.0(Cross project release)
Actual Result:
1. If you select both versions (CPR+PSR) in the filter
The scheduled timeline shows ABC-1 & ABC-2
2. If only Project Specific version is selected it is showing ABC-1
3. If only Cross Project Specific version is selected it is showing ABC-2
Actual result:
The timeline should show ABC-1 & ABC-2 when CPR is selected.
since the tickets are part of same CPR
I still not able to figure out why ABC-1 is not appearing on the timeline when only Cross project release is selected.
I am struggling with similar displaying problem.
Perform following.
Why can't Portfolio show timeline and reports for issues having both Releases?
Hi @rahuldanwade,
We were unable to reproduce this. Could you provide us with further info to help us reproduce this? It would be good to know the following:
- Was PSR 1.0 part of the CPR 1.0 cross project release?
- Was the story a child of the epic?
- What version of Portfolio were you using?
Thanks,
Portfolio for Jira Server Team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.