Is it possible on the Kanban cards to show completion of “related tasks” or “linked tasks” … i.e. a story would show 5/10 on the cards if 5 of the linked tasks are completed.
Anyone who would like to see this capability needs to vote on this item: [JSWCLOUD-20628] Work with sub-task/Story progress bar element - Create and track feature requests for Atlassian products.
Hi @swagner
There isn't anything built-in that will do that... You could build your own indicator using a custom field and the automation rule functions. Perhaps run the rule on a scheduled trigger (every X hours) and display the custom field on your cards on the board.
Please look here are the documentation on automation rules to get started:
Your Jira site admin should be able to help you with adding a custom field to display this value. If that is restricted, you could put the value in a Label instead.
Best regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.