How do you configure Jira to check for any associated issues are open prior to moving to a done or completed status?
Example. I am using an issue type of Risk and associate it with a Story,Task,etc. I would not want a story,ask,etc to move to a completed-done status until all associated Risks have been mitigate or an separate approval has been made to allow.
thanks you
Dale
Sometimes it's useful to prevent the closure of a risk until all of the mitigation tasks have been completed. I wrote a blog post about that last year: Using sub-tasks with risks. The article has some stuff that's specific to our product, but the principle is generally applicable.
You can put a condition that all subtasks must be closed, but not another issue out of the box. There may be a plugin or scripting may do it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.