Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Prevent issue resolution when associated issues are still open

Dale Dean
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 11, 2017

How do you configure Jira to check for any associated issues are open prior to moving to a done or completed status?

Example. I am using an issue type of Risk and associate it with a Story,Task,etc.  I would not want a story,ask,etc to move to a completed-done status until all associated Risks have been mitigate or an separate approval has been made to allow.

thanks you 

Dale

2 answers

0 votes
David Pinn
Contributor
September 11, 2017

Sometimes it's useful to prevent the closure of a risk until all of the mitigation tasks have been completed. I wrote a blog post about that last year: Using sub-tasks with risks. The article has some stuff that's specific to our product, but the principle is generally applicable.

0 votes
Joe Pitt
Community Champion
September 11, 2017

You can put a condition that all subtasks must be closed, but not another issue out of the box. There may be a plugin or scripting may do it. 

Dale Dean
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 11, 2017

thank you!

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events