Hi!
I am using Jira Premium.
I have created a Plan for the Scrum project.
I created a Program in the plan.
Case study: in the program, you can plan issues and pull them apart in sprints.
But my project already has sprints.
If you change the sprint of the issue in the plan, the changes are not reflected in the project.
Question: Is there any way to set this up?
Hi @Игорь Титов
Welcome to the Atlassian Community
We need to save the changes to jira from plan. To do that click on Review Changes on right top corner and select the changes that need to be saved to jira issue and click save.
Here is the reference document https://support.atlassian.com/jira-software-cloud/docs/save-changes-made-in-advanced-roadmaps/
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I know about the need to save changes.
But I'm talking about something else now.
I have active sprints in my Project.
These sprints are displayed in the timeline of the plan.
I have two User stories in Bonus Sprint 1
I see the same info in the Plan Program
Now, in the program of the plan, I want to move the task to another sprint. Like this in Bonus Sprint 2.
Moving and saving changes.
And I see that the value of Sprint is lost
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.