Project estimations

Gianni Pucciani
Contributor
February 25, 2019

Hello,

I'd like to have some input on the best way to manage two level estimations for IT projects in JIRA.

Context:

- cross applications business projects

- shared resources

- development via subtasks

- tests via XRay

- agile objects (Epics, Story)

When using the agile objects with Epics and Stories, the estimation via native fields is done on these objects. But, one object like a Story goes through analysis, development and test. With 3 possible actors involved. In my project I'd like to estimate the effort needed in each of these 3 domains so that I can reserve the necessary resources.

At the moment I am using some custom fields on the Story object like "BA effort", "Dev effort" and "Test effort". These are high level estimations. Then BA then does a second (more precise) estimation on the Story once it is well defined, Dev the same on Subtasks and Testers the same on Tests.

I'd like to know if anybody has a better approach.

 

1 answer

0 votes
Tanya Gordon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 25, 2019

You could try evaluating the Tracking & Estimation fir Jira app from the marketplace. The only thing is that it's not compatible with Tempo. Other than that, it's a great app!

Gianni Pucciani
Contributor
February 25, 2019

Thank you Tanya!

Interesting app. This addresses part of my problem. If I understand correctly however it does not address the two phases estimation (macro estimation and detailed estimation).

Tanya Gordon -HP-
Contributor
February 27, 2019

Hi Gianni Pucciani,

Correct me if I don't understand the process completely, but if you do go over the story and re-estimate it after it's better defined, than the first estimation is meaningless and can be potentially deleted. You can use a post function on a specific transition to clear the existing estimation and let the BA/Dev/Test redefine it on their specific roles, as defined by Tracking & Estimation fir Jira. The total effort of all the roles will be automatically summarized and displayed at the story level Time Tracking fields. 

Cheers,
Tanya

Gianni Pucciani
Contributor
February 27, 2019

Hello Tanya,

I understand what you mean. For us the point of keeping the first estimation is to collect reports on their accuracy. 

Cheers,

Gianni