Hello all,

Is there a way to export the 'Due Date' & 'Due date' for recent 4 weeks? I believe my admin modified 'Due date' to 'Baseline end date'. We are looking for a way to track the change to those dates. Please help.

JIRA Due Date.JPG

1 answer

0 votes
Kian Stack Mumo Systems
Community Champion
September 30, 2023

@Bill Qian

 

Are you asking if you can export values that were previously in a field? I'm not quite sure I understand your question.

 

Thanks,

Kian

Bill Qian
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 2, 2023

Hi Kian, 

I failed to find the 'Due Date' from the CSV file exported. I am confused with those 'Custom fields' and 'Comments'. I am looking for a way to get the 'Due Date'  or 'Due date' data.

Thanks,

Bill

Kian Stack Mumo Systems
Community Champion
October 2, 2023

@Bill Qian

 

Add the due date to your columns prior to exporting.