Question on Burnup and BurnDown chart

VENKATESHWARARAO
Contributor
March 4, 2021

Hi,

 

We have a questions on Burnup and BurnDown charts

1. Is it possible to turn off the counting of sub-task as part of the work scope on Burnup/BurnDown charts.

2. Is there a report available that would show the average BurnUp/BurnDown per team ?

 

Thank you in advance.

 

1 answer

0 votes
Linda Milne_Togetha Group_
Atlassian Partner
March 15, 2021

 

1. depends on the estimation technique you are using, and the config of the report - what are you using?

Have a look at:

https://www.atlassian.com/agile/tutorials/burndown-charts

https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-burndown-chart/

You might be able to tweek the report with your estimation and report configs.

Or, you could create a new board with a filter that excludes sub-tasks - reports use the board filter.

 

2. https://community.atlassian.com/t5/Jira-questions/How-to-see-velocity-chart-report-of-all-sprints/qaq-p/835226, might give you what you need.

Suggest an answer