Hi,
We have a questions on Burnup and BurnDown charts
1. Is it possible to turn off the counting of sub-task as part of the work scope on Burnup/BurnDown charts.
2. Is there a report available that would show the average BurnUp/BurnDown per team ?
Thank you in advance.
1. depends on the estimation technique you are using, and the config of the report - what are you using?
Have a look at:
https://www.atlassian.com/agile/tutorials/burndown-charts
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-burndown-chart/
You might be able to tweek the report with your estimation and report configs.
Or, you could create a new board with a filter that excludes sub-tasks - reports use the board filter.
2. https://community.atlassian.com/t5/Jira-questions/How-to-see-velocity-chart-report-of-all-sprints/qaq-p/835226, might give you what you need.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.