i want to add new status for Epics and Stories - I created a workflow and assigned it to a workflow scheme.
But can't activate this yet as the project does not appear to be allowed to link to workflow scheme in order to activate.
I have basic status (i.e. to do, in progress and done) which is not allowing me to manage day to day project work. I have admin access
Hi Dharmesh - Welcome to the Atlassian Community!
You cannot change out Workflow Schemes for Next-gen Projects. You have to modify the originally created workflow by adding and rearranging columns on your board.
If you need additional functionality, you would need to create a Classic software project and move the issues from your Next-gen project to the new Classic project.
Thank you for the prompt reply - understand the constraints
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For team managed projects can i activate a workflow that i created
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.