Hello,
I would like to ask if it is possible to make a task to block another one in an FF (finish to finish) relationship, instead of FS (finish to start).
Thank you.
It is a common question. Dependencies are not really enforced in Jira automatically. So even if you link issue-1 to issue-2 using blocks link type, it is just a type of link. You can use this information in a roadmap or create some reports out of it.
If you use Advanced Roadmaps then there is an option to use concurrent/sequential dependencies.
Ravi
I explained this here in this video.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Ravi Sagar _Sparxsys_
Thank you for your assistance; so if I understood correctly, due to limitations of Advanced Roadmaps vs , e.g., MS Project, I have to manually set the said issues to finish at the same date.
I cannot block somehow issue 1 to be considered as Done, until issue 2 is not finished, correct?
BR,
Vasilis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.