I am trying to add a few extra statuses and transitions after the final resolution screen. When I to this it messes up all the reports and items do not show up as completed even though they are resolved. I have tried adding only yellow in-progress status and also the green "complete" ones. I want to add a few extra steps to move the stories to production after the sprint is complete. What am I doing wrong? I am not sure if there is a way to reconfigure which status the "complete" is based on.
I dug up the answer, the charts are based on the left and right columns of the board. I had added one additional column on the right and that threw off all the charts.