I can create story point estimates for a story, but cannot assign point estimations to tasks individually, where would I set this up? I saw an old question similar to this answered but the answer is no longer the same as the path they described doesn't apply to the new JIRA

1 answer

1 accepted

1 vote
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 28, 2018

Hello Robby,

To use Story points on other issue types, you must change the context of the Story Points field by following the steps below:

- Type gg and search for Custom fields or Navigate to JIRA Settings > Issues > Custom Fields

Find the field Story Points > Click on the Three dots Icon > Configure

- Click Edit Configuration

- On the Issue type selection, select Tasks

- Click Modify

Robby Kang
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 1, 2018

Thank you!

Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 1, 2018

You are welcome, Robby!

Have a nice day.

george.orsler
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 26, 2020

hey @Petter Gonçalves - I tried to follow your flow but I don't see "Configure" in the dropdown (I am highest permission level). 

I've attached a screenshot of dropdown options - please help! thank you!Screenshot 2020-05-26 at 11.43.16.png

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events