Does anyone know how to get/build an age of WIP chart in Jira?

An age of WIP chart shows:

  • All of the workflow steps on the x-axis
  • WIP age on the y-axis (e.g. days)
  • Individual work items' WIP age plotted (time from start of in-progress until now), showing the work item in each step column
  • Mean, Median, and Mode threshold lines...or, percentiles of item thresholds: 50%, 75%...

This is a measurement tool for teams using Kanban to help diagnose workflow issues.

FYI, I'm trying to see this at a glance for the workflow, not repeatedly changing the settings of something like the "control chart" to gather data to plot outside of Jira in another tool.

Thanks!

1 answer

1 vote
John Funk
Community Champion
May 23, 2019

Hi Bill,

We use the Actionable Agile add-on right now for that. They have a fantastic chart for it. 

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 23, 2019

Thanks, John.  We'll take a look.

__Bill