Hello,
I'm trying to automate some tasks and one of them is:
- create a specific task when a new sprint is created
- create subtasks for that specific task
- do some extra stuff like assign users, components and the original time estimate
I just don't seem to get the original time estimate working. The subtasks are created, the assignment of users and components are executed but my audit log says (for each subtask):
Hey,
The error message is appearing because the Time Tracking field is missing from the screen. Please add the Time Tracking field to the create screen for the subtask issue type so that it will work properly.
But I don't have that option?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey,
Not In the automation—you need to add the Time Tracking field to the Create Issue screen. If you're a Jira admin, you can do this under Project Settings -> Issues -> Screens. Then, under the subtask issue type, go to the Create Issue operation screen and add the Time Tracking field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That did the trick! Thanks, I saw that solution somewhere else, but I had no clue it had to be added to that particular screen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.