Automatically Open Parent task when any sub-task is Opened

Thyagaraj Gopalakrishna October 28, 2019

Anybody can post the steps here to configure a jira project to automatically open the parent task if any of it's sub-task is reopened. I have been searching to configure this, but couldn't find the exact steps.

 

Any help is appreciated!

1 answer

1 vote
Avinash Bhagawati {Appfire}
Community Champion
October 28, 2019

Hi @Thyagaraj Gopalakrishna ,

With the help of Automation for Jira app you will be able to create automation rule to open the parent.

Please find below rule configuration for the same.

Screenshot 2019-10-29 at 11.54.46 AM.png

Thanks,

Avinash

Thyagaraj Gopalakrishna October 29, 2019

@Avinash Bhagawati {Appfire} Thanks for replying. Is this not possible without any additional add-on. Is this possible with any post-function configuration?

Mohamed Benziane
Community Champion
October 29, 2019

Hello,

Unfortunately it's not possible without plugin.