Automatically extend end date if task is not compete/closed

Steven Gray
Contributor
February 17, 2020

We have Big Picture in and working within our team, but I am currently spending alot of time manageing the dates entered for the various tasks where we have not completed a task when we planned to.

 

I have taken a baseline at the start of the project but managing the actual is proving difficult as the end dates used by Big Picture do not update to reflect what is actually happening.  

 

Is it possible to configure the software to do this?

2 answers

0 votes
Tomek-SoftwarePlant
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 6, 2020

Another approach you may try (in case you log time against tasks) is mapping the "Time spent + Remaining estimate" to the End date field. 

Zrzut ekranu 2020-03-6 o 14.23.56.png

Then, when estimating tasks, they'd be given the same value for the remaining estimate, right? So, for example, a task has the original estimate of 5 days and same for the remaining estimate. Further, if it happens to resources they couldn't make it in 5 days and they've logged 8 days of work, the task bar would be automatically stretched. 

Would something like this work for you? 

Steven Gray
Contributor
March 6, 2020

Thanks,  that could indeed work.  I will try it and let you know.  

Tomek-SoftwarePlant
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 6, 2020

Sure :) 

0 votes
Alexander Pappert
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 17, 2020

you could create a JQL search for open issues with "due date < today"

then make a bulk change and increase the due date.

 

or fully automated with some jira addons like automation for jira or scriptrunner.