Hi @Jeff Murray ,
So I am trying to better understand your goal here. What to you hope to achieve? How will the dat be used? Obviously comparing one epic against another would be very difficult given all the variables. Maybe you are looking for something different?
in any event let me offer the following ideas:
May i ask you your advice as i have similar ask with Jeff's request. I am new with jira. Appreciate your guidance as I need to make an automation to create a Sprint Epic for each future Sprint 4 weeks ahead. Each sprint is 2 weeks duration (starting 1 Jan 2024 and end 14 jan 2024 as the 1st Sprint Week 01 2024 then 15 jan 2024 till 28 jan 2024 as our 2nd Sprint Week 03 2024).
The query is similar to the initial but i just need to do the creation (no need automation for closure or tracking). I understand from other post to use the Send web request Action, but i do not understand how to get the details for the https field, the header part and how/where to know "originBoardId" details within my project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kaniawati Zainal Abidin , I recommend posting another question specific to your needs so that it will receive the appropriate attention.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yeah, i was trying to create new post but not sure how to get/create new item in this forum. can advice please. Sorry asking basic question from a newbie, i got lost (as could not find the community forum with the topic) & luckily you posted and it had an email that i could come back here. Sorry for my dumbness...
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You should see "Ask the Community +" in the menu at the top of this page. Click there and choose "Ask a Question".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Jeff Murray
Do you want to know how many days it took an epic to go from To-Do to Closed? There is no straight forward way to get this info OOTB.
You can either look for third party add-ons which do this for you, OR, you set up automation rule which start tracking when Epic transitions from initial stage to next stage and when Epic ends in terminal stage, capture these dates in unused field/issue entity and find the difference that way. You doing this yourself is a go forward solution. Finally, with any approach, Sprints to complete is tough to implement because of unknowns on your sprint schedule and when sprint starts /ends.
Personally, I think its easiest is to evaluate third party add-ons so you can focus on productivity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.