Automation frustration

Beth Wilkinson
Contributor
August 25, 2023

When I have an automation created to create subtasks when a task is created, it is instantly marking them all as Done. What am I doing wrong? 

I'm not sure what you will want to see but here are some screenshots:JIRA-TEAMS.png
J.pngJIRA-TEAMS3.png

2 answers

1 accepted

2 votes
Answer accepted
Trudy Claspill
Community Champion
August 25, 2023

Hello @Beth Wilkinson 

When you say "it" is getting marked as Done, do you mean the newly created subtasks or the parent issue?

Can you show us the workflow used by subtasks and their parent issue types in this project?

With the images provided have you shown us all the steps in your automation rule?

Can you show us the details of one of the steps where you are creating the subtask?

Can you show us what appears in the Audit Log for an execution of this rule?

 

Issue Status value are grouped into categories. You can tell what category the Status belongs to by the color of its lozenge.

Color = green, Status Category = Done

Color = blue, Status Category = In Progress

Color = gray, Status Category = To Do

 

Looking at the images you provided the subtasks and parent issue are all in the status named "New". That status lozenge is showing green which is an indication that the New status has been assigned to the "Done" Status Category. I don't know who created the New status value, but assigning it to the Done status category doesn't seem right. It should've been assigned to the "To Do" status category.

I asked above to see the workflow for your issues because that will show all the Statuses that the issues can move through and (by color) the Status Category for each status. It will also show how the issues can progress through the statuses.

The first status an issue is set to should be one in the "To Do" (gray) status category.

There may be multiple gray statuses. 

There should be at least one blue status to use when there is work being done on the issues.

And there should be at least one green status that is used to indicate work is complete.

 

Some of this information may be accessible only to users with administrative permissions. You didn't indicate if you have such permissions, so if you are unsure how to access this information just let me know and I can provide more guidance.

Beth Wilkinson
Contributor
August 25, 2023

I need sleep lol!

 

Thank you so much!!! I didn't even notice the color of the category and once I updated that, it now doesn't instantly show as completed!

Like # people like this
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2023

Curiously...subtask CORE-48 shows as Resolved and in a status of New.

Trudy Claspill
Community Champion
August 25, 2023

Yep, because the New status was put into the Done Status Category.

Like Bill Sheboy likes this
0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2023

Hi @Beth Wilkinson 

I wonder if there is another rule running which is doing this.  When you look at the history for the subtasks, what/who does it say is moving them to Done?

Kind regards,
Bill

Beth Wilkinson
Contributor
August 25, 2023

It does not say, both the Task and the Subtasks are being created as Done which seems very weird to me...

This is the subtask history:
JIRA.png

This is the task history:

JIRA2.png

Suggest an answer