Big Picture Gantt config

Krishantha February 28, 2023

How do I configure the Big Picture Gantt, to update the gantt view with "due date" and not "end date" field from my Epics?

1 answer

1 accepted

0 votes
Answer accepted
Valerie Knapp
Community Champion
February 28, 2023

HI @Krishantha , thanks for your question.

This is something you can configure in the settings for the application here -

image.png

You can choose to map the dates onto the Jira native fields instead of the BigPicture ones, such as due date instead of end date.

I hope this helps. 

Cheers

Krishantha February 28, 2023

Thank you, this was very helpful. 