Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

BigPicture Gantt Chart shows tasks done within last 3 months?

Sandeep Dhindsa October 18, 2018

Does anyone know if the BigPicture Gantt chart can show tasks that have had their status set as "Done", within the last 3 months? If so, how?

I don't want to show tasks that have been completed on my Gantt chart, but think it would be good to be able to show the ones that have been recently completed. 

1 answer

1 accepted

1 vote
Answer accepted
Daniel Deng
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 18, 2018

Hi Sandeep

You can go to configuration of your BP program and create a quick filter as JQL resolved >= endOfDay(-30) , which will narrow down the tasks to the ones closed in the last 30 days.

Sandeep Dhindsa October 18, 2018

Hi Daniel,

Thanks for this, helps me narrow it down... is there a way to include these with all other tasks?

Daniel Deng
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 18, 2018

Hi Sandeep

Yes, you can write your JQL to define whatever the scope you want to see. 

for example, resolved >= endOfDay(-30) or status != closed, which will return issues closed within lats 30 days and the issues not closed.

 

Sandeep Dhindsa October 18, 2018

Thanks Daniel, appreciate the help!

Ericka Samuels
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 18, 2018

you can also add the Resolved field to your perspective so you can see the date it was closed

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events