Our sprints are 2 weeks but our burndown charts span 4 weeks. The trendline in the chart trends for 4 weeks. As you can see in the screenshot, our sprint is Jan 20 - Feb 2. I would expect the trendline to reach zero on Feb 2 but it doesn't hit zero until Feb 15. Consequently, the burndown chart is ineffective at judging the pace of the sprint.
How do I fix my project/board/sprint so it trends to the correct date?
We're using a classic project with a scrum board. I'm an admin but not the owner.
Hi @Jeff Magill
Please check the active sprint close date in the Backlog screen in Jira.
Thanks,
Pramodh