Below is a picture of what I see when I try to access the burnup chart. I thought the burnup chart was meant to monitor sprint progress. If so, why is it asking me to estimate items in the backlog? All the items currently in the sprint are estimated.
Have you inspected the issues in your sprint? Do they each have an original estimate? Are you using SP or Time Estimation? If you are using Classic project is your board configured for estimation?
Thanks for this. We are using story points and the board estimation statistic was set to time remaining. After setting it to Story Points it works now.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.