Can I configure the done status for a sprint ?

Valerie
Contributor
April 6, 2022

Hello hello,

 

I want to change from Kanban to sprints but with our current workflow I get into a lot of issues:

Our workflow contains multiple status from planning to solved to peer review to in production.

Within one sprint the tasks should be move to solved, but of course if I end the sprints all tasks are unresolved since the solved status is an active status. Only in production is a done status. 

Is there a way that I can configure the sprints to have our active status solved as the 'done' status for the sprint? 

 

Or do you have any other ideas?

 

(I could make the solved status as a done status type but that would crash everything else on my side)

1 answer

1 accepted

2 votes
Answer accepted
Fabio Racobaldo _Herzum_
Community Champion
April 6, 2022

Hi @Valerie Fischer ,

"Done" in a Scrum Board are all your statuses mapped in the last column on the right of your board.

Based on your workflow you can add all your statuses at your convenience in that column.

It should fix your issue.

Hope this helps,

Fabio

Valerie
Contributor
April 11, 2022

Hi Fabio, thanks for that ! I will see if that works :)

Valerie
Contributor
April 22, 2022

Hi @Fabio Racobaldo _Herzum_ 

I tried it now but the burndown still only recognizes issues that are resolved as 'done'. Therefore, the stats say that most of the issues are pending although they are in the last column on the right.

Do you have an idea what might cause that?

Thank you!

Fabio Racobaldo _Herzum_
Community Champion
April 22, 2022

Hi @Valerie Fischer ,

please verify that all "done" issues have a resolution field set.

Fabio

Valerie
Contributor
April 22, 2022

Hi @Fabio Racobaldo _Herzum_ ,

 

as stated above that's the exact issue that I have:

"Within one sprint the tasks should be move to solved, but of course if I end the sprints all tasks are unresolved since the solved status is an active status. Only in production is a done status. 

Is there a way that I can configure the sprints to have our active status solved as the 'done' status for the sprint? "

Maybe I need to rephrase and put it in better words. Can I adjust my sprint so that unresolved tasks get acknowledged as done? 

 

I hope that helps? thank you !!!

Fabio Racobaldo _Herzum_
Community Champion
April 22, 2022

Hi @Valerie Fischer ,

you need to move your "active" statuses to the last column on the right in the configuration of your board.

Noel Smyth
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 15, 2022

Hi @Fabio Racobaldo _Herzum_ I tried what you are suggesting and it does not work.  We also use an active status (Staging Sign off) for the last step in a sprint and it is in the rightmost column of our board (which we titled as done), however the status is not resolved.  so our sprint stats are not reflected correctly. 

Any other suggestions are welcome.

many thanks!

Suggest an answer