I've inherited a Jira board after a colleague left, so I'm trying to work with the Epics they created. I'm working with a basic roadmap and our team has completed some work on a few epics, but it is not done yet and the work was put on hold. We want to resume work on the epic, but I don't want to just drag out the end of the bar on the roadmap because it would look like the team has been working on that epic during a time frame when they were not.
Basically I would like to know if there is a way to have multiple bars that span different time frames, for the same epic?
Hi @Lauren Briskin,
Welcome to Atlassian Community!
No, and epic cannot have multiple start/end dates. So the workaround in you case would be to break up the epic in two different ones.
That's what I was starting to think. Thank you for confirming. Appreciate the reply!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.