To transition Sub-tasks according to the Status changes of their parents, incl setting Resolution according to the parent's Resolution when the parent Issue is set to Done.
Branch 1
Branch 2
Status transition works fine, the Sub-task always transitions to the same Status as the parent, but the Sub-task's Resolution is never set when the parent is set to Done (regardless of what Resolution is chosen).
Jira automation doesn't register it as an error so I guess it could be me that messed up the logic.
Hi @Martin Karlsson ,
Can you share the audit log response. i.e. Open the automation rule audit log, click "Show more" against the incomplete rule and click on expand arrow. This will show why action was not performed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ah, I found the solution.
I moved the action to edit the Resolution Field to the other branch. I had misinterpreted the If conditions in the two branches as referring to the Status of the triggering Issue rather than the Status of the Sub-task --> the condition to copy the Resolution Field was never fulfilled when I set the trigger Issue to Done... I think =)
It works as I want it to now, thanks anyway!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.