×I want to know if I can have an Epic in one project but then link it a task/subtask in another project? Please advise.
Yes, it is possible, the epic does not have to be in the same Jira project as the task/sub-task.
Ok cool - thanks! Any special config I need to set or is it standard?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is standard, so no configuration is needed.