Change Sprint Completion Date

Hans-Hermann Hunfeld
Contributor
May 22, 2012

Is there a way to change the Sprint completion date in the past?

As because nobody really closed the sprint while it s planned end and i realized this some days later i tried to set the correct date which is in the past, but i couldn t find any option how to do this.

Any hints or did i miss something?

1 answer

0 votes
Kelly Garcia
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 7, 2012

I'd like to know how to do this, too.

BBury June 6, 2019

I am interested in this as well. The end date of a sprint means nothing when compiling a sprint report, but rather the completed date which is dependent on when the user clicked on "Complete Sprint." This is terrible and means the sprint end date is simply for aesthetic purposes. :-(

bluemyria November 5, 2019

Please upvote this related issue https://jira.atlassian.com/browse/JSWCLOUD-16331 so that it can get fixed soon!