Hi All,
Client is asking to Automatically update the “Start Date” field with the current date each time an issue’s status is updated to “In Progress”.
Does anyone have any guidance or directions on going about completing this?
Many Thanks,
Z
Hi,
It seems feasible with an addon like scriptrunner or Automation.
I don't know JMWE but there is this documentation to start