Hey there,
We've completed 7 previous sprints and all the user stories within them are set to done, however they've all moved back into the backlog?
is there a way of checking why it has done this, annoyingly this bulks out our backlog to sort out for future sprints and Ideally I don't want to have to drag 200+ Stories into their respective sprints again under the backlog screen.
nothing has changed for these User Stories but randomly they all appeared yesterday, was there a patch or platform update, that could have caused this?
I would guess that someone reconfigured your board in such a way that the issues no longer fall into the last column on it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You should be able to go back into the board configuration and put all the status mappings back in a correct configuration. This mostly means ensuring the status "done" (and any other "end of workflow" status) is in the very last column on the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.